The sporting hall in Bierun

project description

Location was chosen beyond the existing park adjacent to the high school The hall is its additional closure thus adding spatial value. The building is situated on a slope and makes use of the vertical difference of the terrain. The aisle as well as the direct entrance to the auditorium are above the level of the hall's playground and above auxiliary facilities which also serve the outdoor playground.

project facts

Site area: 2,5 ha
Usable floor area: 3269 m2
Total area: 3948 m2
Volume: 25 737 m3
Design: 2002-2003
Construction: 2004-2006
Cost of investment: (building and outdoor sportfacilities) 15 mln PLN

authors

Krzysztof Banaszewski
Jan Strumiłło
Jakub Szczęsny
Ryszard Szczęsny

foto:
Błażej Pindor

by project advancement
ekran003 MHP impresja net4 Polish Spring_Jakub Szczesny_Birzeit2009_5 kro ele DSC_0230 michal jonca IMG_0361 plakat Red Bull Room_1_fot Paweł Fabjanski Red Bull Photofiles LACE1 note 4 Corelation_Wsp MWWwnetrzazoom WWR 05 IC 025 WROC render3 HOO 02schematy_przekro polin3 TAMKA_pano1 mis_makieta OHEL_front view_3 STAD schemat podstawowy 600 027_1 006_1 012_1 026_1 SYNCHRONICITY_light installation in Warsaw_centrala HAR_render_czerwony_mini Centrala_holon_synchronicity1 F2F8-Programm ARC4 001_1 002_2 031_6 005_1 007_3 DSC_0239 010_1 032_2 024_1 028_4 016_1 036_6 G023_1 RM net 2 015_3 035_1 038_3 009_2 008_3 miszmaszintro LUK foto3 G004C_7 030_4 architektursalon2 WYD-parter-bia